Weekly/Monthly Fire Pump Testing
Pump House Conditions:
- Heat is adequate, not less then 4.4°C (40°F) [21°C (70°) for pump room with diesel pumps without engine heaters]
- Ventilating lourvers are free to operate
Pump System Conditions:
- Pump suction and discharge and bypass valves are fully open.
- Piping is free of leaks.
- Suction line pressure gauge reading is normal.
- System line pressure gauge reading is normal.
- Suction reservoir is full.
- Wet pit suction screens are unobstructed and in place.
Electrical System Conditions:
- Controller pilot light (power on) is illuminated.
- Transfer switch normal pilot light is illuminated.
- Isolating switch is closed – standby (emergency) source.
- Reverse phase alarm pilot light is of and normal phase rotation pilot light is on.
- Oil level in vertical motor sight glass is normal.
Diesel Engine System Conditions:
- Fuel tank is two-thirds (2/3) full.
- Controller selector switch is in auto position
- Batteries’ (2) voltage readings are normal.
- Batteries’ (2) charging current readings are normal.
- Batteries’ (2) pilot lights are on or battery failure (2) pilot lights are off.
- All alarm pilot lights are off.
- Engine running time meter is reading.
- Oil level in right angle gear drive is normal.
- Crankcase oil level is normal.
- Cooling water level is normal.
- Electrolyte level in batteries is normal.
- Batter terminals are free from corrosion.
- Water-jacket heater is operating.
*Steam system conditions: Steam pressure gauge reading is normal
- *Testing.
- A weekly test of fire pump assemblies shall be conducted without flowing water.
- This test shall be conducted by starting the pump automatically.
- The electric pump shall run a minimum of 10 minutes.
- The diesel pump shall run a minimum of 30 minutes.
- A valve installed to open as a safety feature shall be permitted to discharge water.
- The automatic weekly test timer shall be permitted to be substitured for the starting procedure.
- *Weekly Tests
- Qualified operating personnel shall be in attendance during the weekly pump operation.
- The pertinent visual observations or adjustments specified in the following checklists chall be conducted while the pump is running:
- Pump System procedure:
- Record the system suction and discharge pressure gauge readings
- Check the pump packing glands for slight discharge
- Adjust gland nuts if necessary
- Check for unusual noise or vibration
- Check packing boxes, bearings or pump casing for overheating
- Record the pump starting pressure
- Electrical system procedure:
- Observe the time for motor to accelerate to full speed
- Record the time controller is on first step )for reduced voltage or reduced current starting)
- Record the time pump runs after starting (for automatic stop controllers)
- Diesel engine system procedure:
- Observe the time for engine to crank
- Observe the time for engine to reach running speed
- Observe the engine oil pressure gauge, speed indicator, water, and oil temperature indicators periodically while engine is running
- Record any abnormalities
- Check the heat exchanger for cooling water flow
- Steam system procedure:
- Record the steam pressure gauge reading
- Observe the time for turbine to reach running speed